Context of 'December 5, 2003: DCAA Audit Finds Halliburton Overcharged on Fuel Imports and Has Failed to Provide Timely Cost Estimates'

This is a scalable context timeline. It contains events related to the event December 5, 2003: DCAA Audit Finds Halliburton Overcharged on Fuel Imports and Has Failed to Provide Timely Cost Estimates. You can narrow or broaden the context of this timeline by adjusting the zoom level. The lower the scale, the more relevant the items on average will be, while the higher the scale, the less relevant the items, on average, will be.

Kellogg Brown & Root, a subsidiary of Halliburton, wins a 10-year no-bid contract to provide the Pentagon with support services in Iraq—everything from fighting oil-well fires to building military bases to feeding and housing soldiers. Vice President Dick Cheney is the former CEO of Halliburton. When he was defense secretary under George H. W. Bush, Cheney had pushed to outsource many of the military’s logistical and support functions to private contractors, part of what Vanity Fair will later term “a broader effort to transfer government functions of all kinds to the private sector.” [Vanity Fair, 2/2009]

Entity Tags: US Department of Defense, Halliburton, Inc., Richard (“Dick”) Cheney, Kellogg, Brown and Root

Timeline Tags: Events Leading to Iraq Invasion

After the US invades Iraq (see March 19, 2003), the US Department of Defense begins drastically curbing its oversight of private contractors providing logistical support to US troops, while at the same time ramping up its outsourcing of critical troop support jobs. The prime beneficiary of the Defense Department’s decisions is former Halliburton subsidiary KBR. While Army contracts will quadruple from $23.3 billion in 1992 to $100.6 billion in 2006, the Army halves its number of contract supervisors, from 10,000 in 1990 to 5,500 in 2007. As a result, fraud runs rampant (see October 2006 and Beyond). Subcontractor Christopher Cahill, whose company has spent a decade working under the LOGCAP logistics program, will say: “I think we downsized past the point of general competency. The point of a standing army is to have them equipped.” Cahill will serve 30 months in prison for fraud. A KBR spokeswoman will say, “Ethics and integrity are core values for KBR.”
Monitoring - Military auditors claim they closely monitor the various layers of KBR subcontractors who actually perform most of the LOGCAP work, but prosecutors will show that US-based auditors can manage reviews that are limited at best over the plethora of deals constantly being brokered between KBR and a host of multinational subcontractors. One of KBR’s Houston office buildings houses a 25-member team from the Defense Contract Audit Agency; in 2007 they will admit that they cannot perform any oversight because they have “no communications” with any “personnel on the ground” in Iraq or Kuwait.
Consequences - Without oversight, many KBR officials begin openly displaying and bragging about the Rolex watches, leather jackets, prostitutes, and other “perks” provided to them by Middle Eastern businessmen. “[T]he KBR guys weren’t shy about bragging about the fact that they were being treated to all that stuff,” according to Paul Morrell, whose firm the Event Source ran several mess halls as a KBR subcontractor. In return, subcontractors become indispensable to the logistical functioning of the Army, and throw their weight around. Former KBR subcontract manager Harry DeWolf will say that when subcontracts came up for renegotiation, the firms would say: “‘Fine, we’re going to pull out all of our people and equipment.’ They really had KBR and the government over the barrel.” [Chicago Tribune, 2/20/2008; Chicago Tribune, 2/21/2008]

Entity Tags: US Department of Defense, Christopher Cahill, Harry DeWolf, Kellogg, Brown and Root, Paul Morrell

Timeline Tags: Iraq under US Occupation

The US Army Corps of Engineers awards Halliburton subsidiary, Kellogg, Brown & Root (KBR), a sole-source monopoly contract to repair and operate Iraq’s oil infrastructure. The contract is awarded in secrecy without any competing bids from other qualified companies. Halliburton will eventually charge the government $2.4 billion for its work. The Defense Contract Audit Agency will find that about $263 million of these costs are either questionable or unsupported. Despite this, the US Army will pay Halliburton all but $10.1 million, or 3.8 percent, of the disputed costs. [New York Times, 2/27/2006; US Congress, 3/28/2006, pp. 3-4 pdf file]

Entity Tags: Defense Contract Audit Agency, Halliburton, Inc., US Army Corps of Engineers

Timeline Tags: Iraq under US Occupation

The Pentagon’s Defense Contract Audit Agency sends a draft audit report to Halliburton subsidiary Kellogg, Brown, & Root (KBR) claiming that the firm overcharged the US military as much as $61 million for fuel deliveries into Iraq. The report says that KBR charged an average of $2.64 per gallon, more than twice the price others were paying. The DCAA also says the company has been slow to provide cost estimates for its projects in Iraq. KBR has given the US government estimates for only 12 orders. As of this date, 69 are overdue. [New York Times, 12/12/2003]

Entity Tags: Defense Contract Audit Agency, Halliburton, Inc.

Timeline Tags: Iraq under US Occupation

The US Army Corps of Engineers (US ACE) issues a waiver relieving Halliburton of the obligation to provide the government with “cost and pricing data” for the fuel it sells to the US military. The company was recently accused of overcharging the military as much as $61 million for fuel deliveries into Iraq (see December 5, 2003). The waiver will make it difficult for auditors to determine whether Halliburton or its Kuwaiti subcontractor overcharged the US government. [US Congress, 1/6/2004 pdf file]

Entity Tags: Halliburton, Inc., US Army Corps of Engineers

Timeline Tags: Iraq under US Occupation

After reviewing $57 billion worth of Iraq reconstruction and troop support contracts through September 2006, auditors from the Defense Contract Audit Agency (DCAA) inform the House Committee on Oversight and Government Reform that contractors in Iraq submitted about $5.1 billion in unsupported costs (“unreasonably high”) and $4.9 billion in questionable costs (for which contractors lack proper documentation). About $2.7 billion of these unsupported or questionable billings are from Halliburton alone. [US Congress, 2/15/2007 pdf file]

Entity Tags: Defense Contract Audit Agency, House Committee on Government Reform, Halliburton, Inc.

Timeline Tags: Iraq under US Occupation

Ordering 

Time period


Email Updates

Receive weekly email updates summarizing what contributors have added to the History Commons database

 
Donate

Developing and maintaining this site is very labor intensive. If you find it useful, please give us a hand and donate what you can.
Donate Now

Volunteer

If you would like to help us with this effort, please contact us. We need help with programming (Java, JDO, mysql, and xml), design, networking, and publicity. If you want to contribute information to this site, click the register link at the top of the page, and start contributing.
Contact Us

Creative Commons License Except where otherwise noted, the textual content of each timeline is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike