This is a scalable context timeline. It contains events related to the event August 27, 2005: Halliburton Contract Critic Demoted. You can narrow or broaden the context of this timeline by adjusting the zoom level. The lower the scale, the more relevant the items on average will be, while the higher the scale, the less relevant the items, on average, will be.

The US Army Corps of Engineers awards Halliburton subsidiary, Kellogg, Brown & Root (KBR), a sole-source monopoly contract to repair and operate Iraq’s oil infrastructure. The contract is awarded in secrecy without any competing bids from other qualified companies. Halliburton will eventually charge the government $2.4 billion for its work. The Defense Contract Audit Agency will find that about $263 million of these costs are either questionable or unsupported. Despite this, the US Army will pay Halliburton all but $10.1 million, or 3.8 percent, of the disputed costs. [New York Times, 2/27/2006; US Congress, 3/28/2006, pp. 3-4 pdf file]

Entity Tags: Defense Contract Audit Agency, Halliburton, Inc., US Army Corps of Engineers

Timeline Tags: Iraq under US Occupation

Halliburton issues a press release declaring that it has won a contract from the US Army Corps of Engineers to extinguish oil well fires and do emergency repairs to Iraq’s oil infrastructure in post-invasion Iraq. The firefighting work will be subcontracted to Houston-based companies Boots & Coots International Well Control, Inc. and Wild Well Control, Inc. [Halliburton, 3/24/2003]

Entity Tags: Halliburton, Inc.

Timeline Tags: Iraq under US Occupation

The US Army Corps of Engineers (US ACE) issues a waiver relieving Halliburton of the obligation to provide the government with “cost and pricing data” for the fuel it sells to the US military. The company was recently accused of overcharging the military as much as $61 million for fuel deliveries into Iraq (see December 5, 2003). The waiver will make it difficult for auditors to determine whether Halliburton or its Kuwaiti subcontractor overcharged the US government. [US Congress, 1/6/2004 pdf file]

Entity Tags: Halliburton, Inc., US Army Corps of Engineers

Timeline Tags: Iraq under US Occupation

Bunnatine H. Greenhouse, the highest ranking contracting official at the US Army Corps of Engineers (USACE), testifies before the Democratic Policy Committee. She criticizes how the Restore Iraqi Oil (RIO) contract was awarded to Halliburton subsidiary Kellogg, Browning, & Root (KBR). “I can unequivocally state that the abuse related to contracts awarded to KBR represents the most blatant and improper contract abuse I have witnessed during the course of my professional career.” She notes that there were several irregularities in the USACE’s contract with KBR to restore Iraqi oil:
bullet The independence of the USACE contracting process was severely compromised. The Office of the Secretary of Defense (OSD) controlled “every aspect of the RIO contract,” even after responsibility for the contract was delegated to the US Army.
bullet She questioned why the Defense Department had delegated executive agency authority for the RIO contract to the Corps when it has no competencies related to oil production. Such work was outside the scope of its congressionally-mandated mission.
bullet The Defense Department paid KBR to prepare for oil production restoration work before the RIO contract was even awarded. The payments were made under the already operational Logistics Civil Augmentation Program (LOGCAP), the scope of which did not include such work. Greenhouse said that the US government should have signed a new contract with KBR for this work. When she questioned the legality of these payments, she was incorrectly told that a new contract was being issued. [Democratic Policy Committee, 6/27/2005 pdf file]

Entity Tags: Bunnatine H. Greenhouse, Democratic Policy Committee, US Army Corps of Engineers, Halliburton, Inc.

Timeline Tags: Iraq under US Occupation

Bunnatine H. Greenhouse, who earlier criticized the US Army Corps of Engineers’ sole-source contract with Halliburton at a public hearing (see June 27, 2005), is demoted from her position as Principal Assistant Responsible for Contracting (PARC). Greenhouse, who was known for her steadfast adherence to regulations enforcing fair competition, received high performance ratings at the beginning of her tenure, which began in 1997. But after she began objecting to the contracts being awarded to Halliburton subsidiary Kellogg, Brown, & Root (KBR), her reviews became negative. [New York Times, 8/29/2005; Democratic Policy Committee, 9/16/2005, pp. 8-9 pdf file]

Entity Tags: US Army Corps of Engineers, Bunnatine H. Greenhouse, Halliburton, Inc.

Timeline Tags: Iraq under US Occupation

Ordering 

Time period


Email Updates

Receive weekly email updates summarizing what contributors have added to the History Commons database

 
Donate

Developing and maintaining this site is very labor intensive. If you find it useful, please give us a hand and donate what you can.
Donate Now

Volunteer

If you would like to help us with this effort, please contact us. We need help with programming (Java, JDO, mysql, and xml), design, networking, and publicity. If you want to contribute information to this site, click the register link at the top of the page, and start contributing.
Contact Us

Creative Commons License Except where otherwise noted, the textual content of each timeline is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike